What’s in a Basement Finishing Contract, and What It Leaves Out

Short answer: In the two basement contracts we read for this article, the price covers the carpentry and finish work: framing, drywall, flooring, doors, trim and paint. Both leave out the materials and the electrical work. One also leaves out plumbing, and one leaves out insulation. Before you sign, ask what is not in the price, who does it, and when it fits into the schedule.

What the two contracts cover

One contract was written for a full basement finish with a new stairway. The other was written for four rooms. Both list their work room by room or trade by trade, and the same items appear in both:

  • Framing. Walls along the concrete, ceiling framing, and in one contract the framing around the heating and cooling ducts so drywall can go up.
  • Enclosures. Both build a closet around the sump pump and enclose the space under the stairs. One also encloses a utility closet; the other builds a mechanical room and a closet around the furnace and the water softener.
  • Drywall. Both include drywall and plastering, then painting. One specifies half-inch drywall and sanding.
  • Floors. Vinyl plank throughout in one; tile in two of the rooms in the other.
  • Doors, baseboards, trim and molding.
  • Trash removal. Both say it is included.

The stairway contract adds an open stairway (one side wall removed), a new railing, balusters and wood treads. If you want to see how these steps follow each other on site, our stages of finishing a basement article walks through them in order.

What they leave out

This is the part worth reading twice.

  • Materials. Both contracts say the price does not include materials. One of them also says the contractor may help buy some materials, gives you the receipts, and asks you to pay for them within 15 days of getting the receipts. The same clause is in the bathroom contracts we read; who buys the materials in a bathroom remodel explains how to plan for it.
  • Electrical. Both say the electrical work is not included. Outlets, switches and lights are still part of a finished basement, so someone has to do them. Wiring runs inside the walls, so it usually has to be done before the drywall goes up. One contract even names the inspection of the framing plus electrical as a step in its payment schedule, which shows the electrical is part of the job’s timeline even though it is not in that price.
  • Plumbing. One contract says the price does not include plumbing labor, and it adds a note next to its bar table: “plumbing not included.” A bar with a sink needs a plumber on top of the carpenter.
  • Insulation. This one differs. One contract includes R-19 insulation on the concrete walls. The other says insulation installation is not included, and its payment schedule mentions spray foam “(3rd party to provide)”. If insulation is not in your contract, ask who provides it and where it fits before the drywall.
  • Rooms left unfinished on purpose. In one contract a room is framed and enclosed, and the contract says to keep it unfinished. The drywall line says “all walls (except in unfinished areas).” If you want part of the basement left as storage or a utility area, write it down so nobody has to guess where the finishing stops.
  • Anything that is not written. Both contracts say they can only be changed in writing, signed by both sides. One adds that work not described in the contract requires more payment.

Upgrades listed as options

Contracts often list upgrades separately from the base scope. The stairway contract lists three soundproofing options, each with its own price line:

  • soundproof insulation between the ceiling joists, in place of the existing insulation;
  • soundproof foam boards between the joists and the drywall; and
  • thicker five-eighths-inch ceiling drywall in place of the half-inch.

They are listed as options, not as part of the base scope. If sound traveling to the rooms above matters to you, ask your contractor which options exist and what each one changes, before the ceiling is closed.

“Rough-in”: ask where the work stops

We also wrote an estimate to add a half bathroom to a basement. It covers the framing, a door, drywall on the outside of the bathroom walls and flooring outside it. The inside of the bathroom is left unfinished, and the electrical and plumbing labor is not included.

The estimate was titled “Bathroom Rough-In.” The word does not mean the same thing in every quote: it often means the pipes and wires placed before the walls close, and in this estimate it meant the room’s shell with no plumbing or electrical labor. If a quote uses the word, ask exactly what is done and where the work stops.

Questions to ask before you sign

  • Are materials included? If not, who buys them and when are the receipts due?
  • Is the electrical included? If not, who does it, and when does it fit between the framing and the drywall?
  • Is plumbing included, for a bar, a bathroom or a laundry?
  • Is insulation included? On which walls, what kind, and who installs it?
  • Which areas are finished and which are left unfinished?
  • Which upgrades are listed as options, and what does each one change?
  • Who applies for the permits? Our contractor check article explains what a Massachusetts home improvement contract has to say about it.
  • How is a change written down and signed?

When you compare two quotes, compare what is in each, line by line.

Checklist

  • Materials, electrical, plumbing and insulation each marked “included” or “not included”
  • Finished and unfinished areas named
  • Options listed separately and named
  • Permits: who applies
  • Changes in writing, signed by both sides
  • Payment steps tied to the stages of the work, as described in what each payment is tied to

FAQ

Does a basement finishing quote include electrical work? In the two of our contracts that we read, no: both say the electrical work is not included. Ask for it in writing, either as a line in the contract or as a separate quote.

Can part of the basement stay unfinished? Yes. One of our contracts framed a room and kept it unfinished on purpose. Name the room and say what “unfinished” means for it, so the drywall, floor and paint lines are clear.

Why do two basement quotes look so different? They may not cover the same things. One may include insulation, plumbing or electrical and the other not. Compare the scope line by line before you compare anything else.

Liang Yu works in marketing at Sun Shore Construction and has been with the team for three years.

Planning a basement or bathroom remodel? Get a free in-home estimate: call us or fill out the form on sunshoreconstruction.com.

Language »
(857) 858-2600 Call Now Free Estimate